Scope of Work
- Replacing north side windows, doors and railings
Project Cost:
- State Historical Fund $109,225
- CSDB Match $36,409
- Total $145,634
Construction: November 2022-March 2023
Scope of Work
- Replace existing slate and built-up roofing, gutters, downspouts and flashings
Project Cost: $1,443,067
Construction: June 12, 2023-August 3, 2023
Scope of Work
- Replace existing slate and built-up roofing, gutters, downspouts and flashings on West Hall
Project Cost: $689,611
Construction: July 5, 2023-October 31, 2023
Scope of Work:
- New Fire Suppression System
- Ceiling Work
- LED Lighting
- New ADA-Compliant Public Restrooms
- HVAC/Mechanical Upgrades
- Asbestos Abatement
- Flooring Replacement
- Security
Project Cost: $3,767,137
Construction: May 30, 2023-October 31, 2023
Scope of Work:
- Repair roof parapet
Project Cost: $75,000
Construction: June 2023-July 2023