Scope of Work
- Design and construct a universally accessible playground
Project Cost $1,954,154
Construction: May 13 - August 9, 2024
Scope of Work
- Replace existing slate and built-up roofing, gutters, downspouts and flashings
Project Cost: $1,443,067
Phase 2 Construction: June 20, 2024-August 2, 2024
Scope of Work:
- New Fire Suppression System
- Ceiling Work
- LED Lighting
- New ADA-Compliant Public Restrooms
- HVAC/Mechanical Upgrades
- Asbestos Abatement
- Flooring Replacement
- Security
- Elevator
- Upper Gym Improvements
- New Drinking Fountains
- New Door Hardware
Project Cost: $5,319,059
Phase 3 Construction: June 20, 2024 - October 31, 2024
Scope of Work:
- Campus Wide Security Assessment
- Fiber and Network Improvements
- Design and Install Campus Wide Surveillance System
- Perimeter Fence and Campus Lighting Improvements
Project Cost: $2,571,426
Construction:
- Fiber/Network Improvements May - June 2024
- Site Improvements June - August 2024
- Surveillance System October 2024 - January 2025